Netherfield Road: Update from the Clancy Group

Please see below a brief update from the Clancy Group of works at Netherfield.

Rising main installation works completed week commencing 10th June 2024:

We have completed the finishing works in washout chambers WO03 & WO04.

Started excavating the trench line into Netherfield WTW between CH40 & CH0.

The new rising main has been installed up to Uckham Lane (CH5370) a total of 4,965 metres have been installed to date.

The rest of the rising main in Darvel Down will be completed during the summer school holidays.

Work we are aiming to complete week commencing 17th June 2024

Works in the access track to Netherfield WTW is continuing between CH0 to CH40.

We will be carrying out a trial hole within Netherfield WTW, next to the sludge tank.

We are carrying out the pressure testing of the pipeline on Monday 17th and Tuesday 18th June, the road will be closed between the junction of wattles wish and the bridge.

 Please see the below the diagram showing the section of the road where we are working.