Netherfield Road Update from the Clancy Group

Please see below a brief update on the progress of our works along Netherfield Road.

180mm rising main installation:

We have installed 260 metres of the new rising main this week up to CH4760 (Total of 4,155 metres has now been installed to date).

Netherfield Road was reinstated on Saturday 9th March and the barriers will be cleared on Sunday 10th ready for Clancy TM to temporary open Netherfield Road on Monday morning.

Once Netherfield Road has been reopened, we will be setting up 2-way traffic lights on the A2100 and closing the junction of Virgins Lane.

Week commencing 11th March 2024

We will be carrying on with the open cut works in Wattle’s Wish and carrying out preparation works on the A2100 and Virgins Lane up to CH5000.

Construction works will also continue on compound No2 on Netherfield Road.

Please see the below diagram showing the section of road where we are working.