Netherfield Road Update from the Clancy Group

Please see below a brief update on the progress of our works along Netherfield Road.

180mm rising main installation:

We haven’t installed any of the new rising main this week due to completing preparation works in Wattle’s Wish and constructing our new compound (Total of 3,895 metres has now been installed to date).

Week commencing 04th March 2024

We will be carrying out preparation works and looking to install the last 200m of the new rising main up to CH4700 on Netherfield Road and we will also be looking to lay 80m of the rising main via open cut methods in Wattle’s Wish up to CH4780 .

Please see the below diagram showing the section of road where we are working: