Netherfield Road Update from the Clancy Group

Please see below a brief update on the progress of our works along Netherfield Road.

180mm rising main installation:

We have installed 200 metres of the new rising main this week up to CH4040 (Total of 3,435 metres has now been installed).

Monday 5th February the team will be carrying out reinstatement works up to CH3980 to shorten the site down, we will then be carrying out preparation works and looking to install a further 300m of the new rising main up to CH4340. Please see the below diagram showing the section of road where we are working.