Netherfield Road Update – 9 October 2023

Please see below a brief update on the progress of the Clancy Group works along Netherfield Road.

Main compound construction works:

The main compound hardstanding area has now been constructed and site cabins have been delivered and lifted into position also the site perimeter fencing is 90% completed and will be finished on Tuesday 10th October.

180mm rising main installation:

We have installed 285m of the new rising main this week (total 385m installed to date) and started to backfill and reinstate the trial holes excavations to move the road closure further down the road.

For next week we are planning to make the connections and backfill the launch and reception pits including the rest of the trial holes and install another 200m of pipe although this is depending on the specialist drilling rig availability.

Please see below as of Monday morning 9th October the road will be fully closed near the Netherfield Village Hall entrance. The residents between the new closure location and Darvel Down will now access their properties from Battle Road / Darvel Down.