Netherfield Road: Update from the Clancy Group

Please see below a brief update from the Clancy Group on the progress of works at Netherfield.

180mm rising main installation:

The new rising main has been installed up to Uckham Lane (CH5370). A total of 4,765 metres have been installed to date and we will restart laying the rest of the rising main in Darvel Down during the summer school holidays.

Netherfield Road is closed for the washout and air valve construction works, we have finished the construction of washout chambers (WO01, WO02, & WO03) and air valve chamber (AV03)

Week commencing 20th May 2024

We will be constructing the air valve chambers (AV02 & AV04) and completing 1st time reinstatement works to AV03, WO03.

Please see the below the diagram showing the section of the road where we are working.