Netherfield Road: Update from the Clancy Group

Netherfield Road: Update from the Clancy Group

180mm rising main installation:

The new rising main has been installed up to Uckham Lane (CH5370) a total of 4,765 metres have been installed to date and we will restart laying the rest of the rising main in Darvel Down during the summer school holidays.

Netherfield Road is closed in the below locations for the washout construction works. We have finished the construction of washout (WO01) this week including 1st reinstatement.

Week commencing 29th April 2024

On Monday 29th April 2024 we will be moving the road closure further down the road to the washout chamber (WO02) location to start the construction works.

Please see the below diagram showing the section of the road where we are working.