Please see below for a brief update from the Clancy Group on the progress of works at Netherfield:

180mm rising main installation:

We have now finished installing the new rising main up to Uckham Lane (CH5370). A total of 4,765 metres have been installed to date and we will restart laying the rest of the rising main in Darvel Down during the summer school holidays. We have reinstalled the road closure on Netherfield Road to start the washout and air valve construction works.

Week commencing 22nd April 2024

We will be finishing the construction of washout chamber WO01 and then start the construction of air valve AV02.

Please see the below diagram showing the section of road where we are working.