Blackfriars Development April Update

Breheny Civil Engineering Ltd are planning to undertake and supervise the following works during this month:
• Management of surface water runoff involving use of water treatment system (dependant on weather conditions).
• Japanese knotweed treatment works in Field 2.
• Demolition of disused shed in Field 3 and removal of asbestos contaminated materials (dependant on weather conditions).
• Continue foul drainage installation in Harrier Lane.
• Commence new footway construction in Harrier Lane.
• Earthworks in Field 2.
• Soil muckaway from Field 1. If you have any queries about the ongoing works, please contact the Breheny Civil Engineering Site Agent, Mr Harayshan Pirabaharan, on Mob. 07399 528626.

Please find attached an update regarding the development at Blackfriars.